The Heights Construction Update: June 3, 2025

Public Infrastructure Work for the Week of June 9

  • Utility crews continued storm sewer installation on Howard Street between Ivy Avenue and Montana Avenue.
  • Roadway crews continued prepping the roadway base on Howard Street between Ivy Avenue and Montana Avenue.
  • Grading crews began prepping Winthrop Avenue between Hoyt Street and future Iowa Street for construction.

Public Infrastructure Work Anticipated Week of June 16

  • Utility crews will continue storm sewer installation on Howard Street between Ivy Avenue and Montana Avenue.
  • Roadway crews will continue prepping the roadway base on Howard Street between Ivy Avenue and Montana Avenue, and Montana Avenue from McKnight Road to Howard Street.
  • Grading crews will continue prepping Winthrop Avenue between Hoyt Street and future Iowa Street for construction.
  • Utility crews will begin sanitary sewer work on Howard Street from Larpenteur to Montana Avenue.