Public Infrastructure Work for the Week of June 2
• Utility crews continued storm sewer installation on Howard Street and Winthrop Street between Ivy Avenue and Sherwood Avenue.
• Roadway crews continued prepping the roadway base on Howard Street between Ivy Avenue and Montana Avenue.
Public Infrastructure Work Anticipated Week of June 9
• Utility crews will continue storm sewer and sanitary service installation on Howard Street and Winthrop Street between Ivy Avenue and Sherwood Avenue.
• Roadway crews will continue prepping the roadway base on Howard Street between
Ivy Avenue and Montana Avenue.
• Grading crews will begin prepping Winthrop Avenue between Hoyt Street and future Iowa Street for construction.