The Heights Construction Update: June 6, 2025

Public Infrastructure Work for the Week of June 2

• Utility crews continued storm sewer installation on Howard Street and Winthrop Street between Ivy Avenue and Sherwood Avenue.

• Roadway crews continued prepping the roadway base on Howard Street between Ivy Avenue and Montana Avenue.

Public Infrastructure Work Anticipated Week of June 9

• Utility crews will continue storm sewer and sanitary service installation on Howard Street and Winthrop Street between Ivy Avenue and Sherwood Avenue.

• Roadway crews will continue prepping the roadway base on Howard Street between

Ivy Avenue and Montana Avenue.

• Grading crews will begin prepping Winthrop Avenue between Hoyt Street and future Iowa Street for construction.